Estimator
FX-TDR-2611-001
Production Planning
Edit phases, crew and actual hours. Alerts compare against crew capacity and shop-wide load.
Planned hours
4,720
Actual to date
1,836
39% of plan
Duration
14 wks
Alerts
2
Timeline
W1
W2
W3
W4
W5
W6
W7
W8
W9
W10
W11
W12
W13
W14
W15
Material procurement
80% · 2 crew
Cutting & rolling
75% · 6 crew
Fit-up & welding
41% · 10 crew
NDT & PWHT
0% · 4 crew
Hydrotest & coating
0% · 6 crew
Shop load (all projects)
Phases & actuals
| Phase | Start wk | Weeks | Crew | Planned h | Actual h | Var. | |
|---|---|---|---|---|---|---|---|
| -24 | |||||||
| -180 | |||||||
| -1,700 | |||||||
| -380 | |||||||
| -600 |
Capacity & bottleneck alerts
- Shop week 6: load 1,918 h exceeds capacity 1,440 h (all projects)
- Shop week 10: load 1,470 h exceeds capacity 1,440 h (all projects)
Shop capacity assumes 2 × default crew (12) × 6 shifts × 10 h — set in Settings.